1. CCCC First Highway Consultants CO., LTD, Xi'an Shanxi 710068, China;
2. Shaanxi Tongyu Research Institute Of Highway CO., LTD, Xi'an Shaanxi 710064, China
Optimum Calculation Method for Cable Force of Concrete-filled Steel Tube Arch Bridge in Inclined Cable-stayed Construction
LI Yang1,2, WANG Jiang-long1,2, GE Su-su1,2
1. CCCC First Highway Consultants CO., LTD, Xi'an Shanxi 710068, China;
2. Shaanxi Tongyu Research Institute Of Highway CO., LTD, Xi'an Shaanxi 710064, China
摘要Iterative initial value of cable force based on influence matrix and linear programming is determined to study the cable force of long-span concrete-filled steel tube (CFST) arch bridge using the cable-hoisting construction method. Considering the effect of tangential displacement, we observed the appropriate cable force through the golden selection method and iterative forward erection. The cable force determination flow and method aimed at the installation shape are analyzed, which shows that the one-off tension of the cable force on a cable-hoisting CFST arch bridge focusing on installation shape is achieved and serves as a reference for similar engineering practices.
Abstract:Iterative initial value of cable force based on influence matrix and linear programming is determined to study the cable force of long-span concrete-filled steel tube (CFST) arch bridge using the cable-hoisting construction method. Considering the effect of tangential displacement, we observed the appropriate cable force through the golden selection method and iterative forward erection. The cable force determination flow and method aimed at the installation shape are analyzed, which shows that the one-off tension of the cable force on a cable-hoisting CFST arch bridge focusing on installation shape is achieved and serves as a reference for similar engineering practices.
基金资助:Supported by the National Natural Science Foundation of China (No.50808019)
通讯作者:
LI Yang,E-mail address:2644332319@qq.com
E-mail: 2644332319@qq.com
引用本文:
李扬, 王江龙, 葛粟粟. 钢筋混凝土拱桥斜拉扣挂施工扣索索力的优化计算方法[J]. Journal of Highway and Transportation Research and Development, 2017, 11(1): 42-48.
LI Yang, WANG Jiang-long, GE Su-su. Optimum Calculation Method for Cable Force of Concrete-filled Steel Tube Arch Bridge in Inclined Cable-stayed Construction. Journal of Highway and Transportation Research and Development, 2017, 11(1): 42-48.
[1] MEI Gai-wei, ZHANG Xiong, GAO Xiong. Calculation Method of Cable Force of Arch Bridge in Cable-hoisting Construction[J].Chongqing Architecture. 2012,108(11), 42-44. (in Chinese)
[2] ZHANG Yu-ping, LI Chuan-xi, DONG Chuang-wen. Discussion on "Zero Moment Method" in the Cable Calculation of Cable-stay[J]. Journal of ChangSha Communications University, 2004, 20(1), 15-18. (in Chinese)
[3] LIU Zhi-hui, YU Guang-yong, QIAO Wen-ting. The Calculating Method Discussion on the Lifting Construction Cable Force of Long-span Concrete-filled Steel Tubes Arch Bridge and Arch Rib[J]. Northern Communications, 2004, (10), 29-32. (in Chinese)
[4] LIU Shu-jie. The Line Shape Control of Steel Box Arch Rib of External Slanted Arch Bridge[D]. Shangghai:Tongji University,2008. (in Chinese)
[5] ZHANG Jian-min, ZHENG Jie-lian, XIAO Ru-cheng. Calculation Method for Optimizing the Installation Process of Concrete Filled Steel Tube Arch Bridge[J]. China Journal of Highway and Transport, 2005, 18(2):40-44(in Chinese)
[6] TIAN Wei-feng, Zhou Shui-xing, QIN Zhen. Modification of Virtual Displacement Based on Unstressed State Method[J]. Journal of Chongqing Jiaotong University (Natural Science), 2010, 29(1):20-22. (in Chinese)
[7] ZHANG Wan-xiao, YANG Chang-long, Zhou Shui-xing, et al. Study on Control Methods for Arch Bridges Constructed Cantilever Construction Based on Unstressed State Method[C]//Proceedings of the 21 National Bridge Academic Conference (Volume 1). Beijing:China Communications Press,2014:785-789. (in Chinese)
[8] DAI Peng, XIE Gong-yuan, HAO Xian-wu, Nonlinear Analysis of Cable-hoisting Construction of Long-span Concrete Filled Steel Tube Arch Bridge[J]. Journal of WuHan University of Technology,2007, 29(2):114-117
[9] ZHOU Ye-jun. Study on Calculation Method of Optimal Stayed-buckle Cable Force for Reinforced Concrete Arch Bridge with Cantilever Cast Method[D]. Chengdu:Southwest Jiaotong University,2008. (in Chinese)
[10] FANG Hong, GAO Qiong. The Influence Matrix in Cable Adjustment of Tied Arch Bridge[J]. Journal of China & Foreign Highway, 2014, 34(6), 146-148. (in Chinese)
[11] SONG Yong-dong, ZHANG Yu-qiang, ZHANG Jian-hua. Optimized PID Parameter Adjustment Technology Based on Golden Section Law[J]. Journal of Xi'an University Engineering, 2007, 21(2), 262-266. (in Chinese)
[12] XIAO Wei. Research on Cable Force Calculation Methods for Construction of Super Long-span CFST Bridge[D]. Chongqing:Chongqing Jiaotong University, 2011. (in Chinese)
[1]
常柱刚, 王林凯, 夏飞龙. 基于CV NewMark-b法桥梁风致振动FSI数值模拟[J]. Journal of Highway and Transportation Research and Development, 2019, 13(2): 28-37.